Project Name: El kurimat power plant ( 3 ) Complex Cycle

Powered of 2*250 mega watt (Gaseous) +1*250 mega watt (steamy)

 
 

Project Location: El kurymat – Atfih – Helwan

Investment cost: 2563 million Egyptian pounds.

Funding resources:  by Self-financing in addition to Egyptian and international financing banks.

Type of bidding: International tenders allow diversity and technological packages in a way that gives us the best price, and to provide the largest share of locally manufactured components.

The technical specifications: the plant consists of:

                                             2*250 mega watt (Gaseous unit) +1*250 mega watt (steam unit)

                                             Overall capacities: 750 mega watt.

                                           Fuel type: natural gas (Major fuel) - Diesel (fuel reserve)

                                           Main transformers: 2*352 Mega volt.A +1*340 Mega volt.A

                                           Transform rate: 15/ 220 KV , 18/220 KV

The connecting lines:  air line dual circle of El kurimat (3)\ 6 October 220 KV Length of 95 KV\ air line dual circle of El kurimat (3) East of Cairo 220 KV Length of 90 KM.

The beginning implementation date: 14/12/2006

The Operation Date: The commercial operate for the one and two gases units in January, June 2009

                       From the supposed the trial operation of the steam unit in June 2010.

 

 

Back

 

 

 

Source: projects report that issued by the Ministry of Electricity and Energy